Location:
|
Azzawiya, Libya
|
Client:
|
Azzawiya Oil Refining Company
|
Year:
|
2007 – ongoing
|
Description:
|
Royal Haskoning is currently developing a new oil harbour for the Azzawiya Oil Refining Company (ARC). The harbour is to be located in Libya, some 50 km to the West of capitol Tripoli. Currently, the ARC refinery operates three buoy moorings for tanker traffic and a small craft harbour for its small tugs, line boats, workboats and similar craft. In an attempt to increase operational efficiency and reliability and reduce downtime, the buoys are to be replaced by a fully protected harbour, providing amongst other for 3 new oil jetties, smaller berths for bunker fuel vessels and tugs etc, and materials offload facility for the planned revamp of the refinery.
Royal Haskoning is responsible for preparations for Site Investigations, Engineering Design Study (‘layout & concept designs’), Front End Engineering Design (FEED), EPC Tendering Assistance, Supervision of Detailed Design and Construction, and overall Management and Administration of the EPC Contract. Our scope includes a/o the design of breakwaters, approach channel & dredging, jetties, quay walls, piping and its routing, tie-in to existing piping and installations, roads, electric cabling etc.
|
|
Sirte New West Port Development |
|
|
|
Location:
|
Sirte, Libya
|
Client:
|
Libyan Port and Maritime Transport Authority
|
Year:
|
2008 – ongoing
|
Description:
|
The Libyan Maritime Transport and Ports Administration (LMTPA) are managing the development of a new port to the West of the town of Sirte, the Sirte Commercial Port (SCP). It is envisaged that the new port will serve as an additional hub port on the Libyan coastline for both import/export and transshipment. This major port will have an ultimate capacity of around 8 million tonnes per year and a total berth length of around 3,000m. Berthing facilities will include provision for Containers, Multi-purpose / general cargo, Bulk import (cereals etc.), Ro-ro and Cruise liner. Royal Haskoning is responsible for the master planning and design for the entire port development, including data collection, specification of additional surveys, master planning and concept designs, final designs.
|
|
Sirte East Commercial Port |
|
|
|
Location:
|
Sirte, Libya
|
Client:
|
LPMTA
|
Year:
|
2007 – ongoing
|
Description:
|
For the Commercial Harbour to the East of Sirte which is currently under construction, Royal Haskoning and Maward Consulting Engineers are providing Technical assistance for the following.
(1) Inspection of the completed main breakwater and review of QA procedures
(2) Detailed design review and construction supervision of berthing structures
(3) Harbour operation strategy study and design of land based facilities
(4) Training and assistance to Owner staff
|
|
|
|
|
|